Nagpur, May 10: The Butibori flyover, which witnessed a structural subsidence of nearly 100 mm in December, is currently undergoing major repair work. The incident disrupted traffic movement on one of the busiest industrial routes connecting Nagpur to Butibori MIDC. Repair Timeline and Current Status Officials involved in the restoration process confirmed that the temporary iron scaffolding installed beneath the affected section will be dismantled within the next 15 days. After this stage, an additional 10 days are expected for reinforcement work and mandatory safety testing. Although the National Highways Authority of India (NHAI) has not officially announced a reopening date, internal estimates suggest traffic could resume within the next 25 days, subject to successful completion of inspections. Structural Reinforcement and Safety Testing The damaged cantilever beams are being strengthened using Carbon Fiber Reinforced Polymer (CFRP) sheets , a modern techniq...